Case studies · 1 min read
97.94% EM Radiation reduction
LSLiveSAFE team
In this article4 sections ⌄
Case Study – 4 JP Nagar
| Before | After |
|---|---|
| Date: 26th June 2020 Time: 12:30 PM Location: JP Nagar | Date: 5th August 2020 Time: 05:00 PM Location: JP Nagar |





Observations
- Observed three towers with multiple 2G,3G and 4G antennas, one at a distance of less than 100m and other two at a distance of 300m from the house audited.
- CTR Reading is observed to be High in Living(1),Media Room(2),Dining(3),Pooja Room(4),Mother’s Room(6),Guest Bed Room(7),Son’s Bed Room(8),Daughter’s Bed Room(9),Study Room(10) and Master Bed Room(11) .
- CTR Reading is observed to be safe in Kitchen (5) .
Recommendations
- Windows area of the Living(1),Media Room(2),Dining(3),Pooja Room(4),Mother’s Room(6),Guest Bed Room(7),Daughter’s Bed Room(9),Study Room(10) and Master Bed Room(11) needs be secured with LiveSAFE Mesh and LiveSAFE Film.
- Wall area of theLiving(1),Media Room(2),Dining(3),Pooja Room(4),Mother’s Room(6),Guest Bed Room(7),Daughter’s Bed Room(9),Study Room(10) and Master Bed Room(11) needs be secured with LiveSAFE Mesh and LiveSAFE Coating.
- Ceiling area of the Living(1),Media Room(2),Dining(3),Pooja Room(4),Mother’s Room(6),Guest Bed Room(7),Daughter’s Bed Room(9),Study Room(10) and Master Bed Room(11) needs be secured with LiveSAFE Coating.
97.94% EM Radiation reduction achieved post LiveSAFE Installation.